DPW Project BI-CTC-407
March 2007
Monthly Report #5

EXECUTIVE SUMMARY

Demolition of the plaza area, the west parking garage and the roof is now completed. 

During the month of March the following significant construction activities have begun and continue:

  • Interior grade beams;
  • Installation of the new seismic brace frame steel;
  • Mobilization of the Crane with the installation of the new steel columns and beams;
  • Delivery of the new steel joists and deck.

During the month of April the following significant construction activities will commence:

  • Installation of beams and metal deck on the second and third floors to close up existing floor openings;
  • Placement of concrete over closed up floor openings on the second and third floors; 
  • Continued erection of structural steel;
  • Placement of the new foundation walls on the west, north and southeast elevations;
  • Conduit runs for power, telephone and data from the existing College into the South Building;
  • Continued cutting of the existing slab on grade in order to install the new MEPS under slab work.

Newfield has updated the Construction Schedule with a data date of March 7, 2007.  As of the end of the month, the construction is on target based on the updated schedule.

The Construction Administrator continues to meet throughout the month with the Project Team chairing the Owner’s Meetings and participating in the General Contractor’s Subcontractor Coordination Meetings.

constructionconstructionconstructionconstruction
constructionconstructionconstructionconstructionconstructionconstructionconstructionconstructionconstructionconstruction

construction

About Us | Site Map | Search | Fac/Staff Directory | Directions | Contact Us
© Housatonic Community College. All Rights Reserved. 900 Lafayette Blvd., Bridgeport, CT 06604. (203) 332-5200