Housatonic Community College
Bridgeport, CT
DPW Project BI-CTC-407
MAY 2007
Monthly Report #7
EXECUTIVE SUMMARY
During the month of May the following significant construction activities have been achieved:
- Placement of concrete over closed up floor openings on the second and third floors;
- Continued erection of structural steel;
- Placement of the new foundation walls on the south and southeast elevations;
- Placement of concrete infills at Slab on Grade over grade beams and MEPS sub slab installations;
- Continued cutting of the existing slab on grade in order to install the new MEPS under slab work.
- Renovation work in the existing Performing Arts Center (PAC);
During the month of June the following significant construction activities will commence:
- Placement of concrete slab infills over underground utilities within the Beacon building;
- Continued erection of Structural Steel at the West and East additions;
- Completion of all new foundation walls;
- Continued installation of hanger assemblies to support future mechanical and electrical systems;
- Drilling of pistons for the two new elevators in the Beacon Building;
- Continued renovation work in the Performing Arts Center.
Newfield has updated the Construction Schedule for Performing Arts Center with a data date of May 1, 2007 and an updated Construction schedule for the Beacon building with a data date of May 18, 2007. As of the end of the month, the construction is on target based on the updated schedules.
The Construction Administrator continues to meet throughout the month with the Project Team chairing the Owner’s Meetings and participating in the General Contractor’s Subcontractor Coordination Meetings.