Housatonic Community College
Bridgeport, CT
DPW Project BI-CTC-407
JUNE 2007
Monthly Report #8
EXECUTIVE SUMMARY
During the month of June the following significant construction activities have been achieved:
- Placement of concrete over closed up floor openings on the second and third floors continues;
- Continued erection of structural steel;
- Placement of the new foundation walls on the southwest elevations;
- Placement of concrete infills at Slab on Grade over grade beams and MEPS sub slab installations continues;
- Continued cutting of the existing slab on grade in order to install the new MEPS under slab work.
- Renovation work in the existing Performing Arts Center (PAC) continues;
- MEPS Trade contractors continue to install hangers from the ceiling to support their future work;
- Spray fire proofing has begun on the second floor;
During the month of July the following significant construction activities will commence:
- Placement of concrete slab infills over underground utilities within the Beacon building;
- Continued erection of Structural Steel at the West and East additions;
- Continued installation of hanger assemblies to support future mechanical and electrical systems;
- Installation of the roofing system beginning on the east side and moving towards the west side;
- The installation of new MEPS beginning on the second floor;
- Continued renovation work in the Performing Arts Center
Newfield has updated the Construction Schedule for the Beacon building with a data date of June 21, 2007. The schedule for the Performing Arts Center has not been updated from the last data date. As of the end of the month, the construction is on target based on the schedules.
The Construction Administrator continues to meet throughout the month with the Project Team chairing the Owner’s Meetings and participating in the General Contractor’s Subcontractor Coordination Meetings.