DPW Project BI-CTC-407
SEPTEMBER 2007
Monthly Report #11

EXECUTIVE SUMMARY

During the month of September the following significant construction activities continue or have been achieved:

  • Placement of concrete over closed up floor openings has been completed; 
  • Continued erection of structural steel;
  • Completion of the new foundation walls;
  • Completion of the placement of concrete infills at Slab on Grade over MEPS sub slab installations;
  • Completion of the cutting of the existing slab on grade in order to install the new MEPS under slab work.
  • Completion of the contractual Renovation Work in the Performing Arts Center (PAC);
  • MEPS Trade Contractors continue to install hangers from the ceiling to support their future work;
  • Spray fire proofing completed on the second floor; substantially completed on the third floor and begun on the first floor;
  • Installation of the new ductwork and chilled water piping continues this period;
  • Installation of  new storm water waste lines within Beacon Hall continued this period;
  • Installation of electrical conduits continued this period;
  • Installation of new sanitary lines continued within Beacon Hall this period
  • Completion of the roofing system at the second floor south wing;

During the month of October the following significant construction activities will commence or continue:

  • Completion of the erection of Structural Steel at the Southwest Addition that will house the future chillers;
  • Continued installation of hanger assemblies to support future mechanical and electrical systems;
  • Continued installation of the new MEPS systems throughout Beacon Hall;
  • Continuation of exterior and interior masonry work;
  • Continuation of exterior cold formed metal framing.

Newfield has updated the Construction Schedule for Beacon Hall with a data date of September 15, 2007.  The schedule for the Performing Arts Center has been not been updated from the last data date.

The Construction Administrator continues to meet throughout the month with the Project Team chairing the Owner’s Meetings and participating in the General Contractor’s Subcontractor Coordination Meetings.

Construction Photos of Beacon Hall (Photos of the Performing Arts Center at end)

Performing Arts Center Remodel

About Us | Site Map | Search | Fac/Staff Directory | Directions | Contact Us
© Housatonic Community College. All Rights Reserved. 900 Lafayette Blvd., Bridgeport, CT 06604. (203) 332-5200