Monthly Report #18
EXECUTIVE SUMMARY
During the month of April the following significant construction activities
continue or have been achieved:
- MEPS Trade Contractors have completed the installation of hangers from the ceiling to support their future work;
- Installation of the new ductwork and chilled and hot water piping has been substantially completed this period;
- Installation of new storm water waste lines within Beacon Hall has been substantially completed this period;
- Installation of electrical conduits continued this period;
- Installation of new sanitary lines substantially completed this period;
- Installation of aluminum window and curtainwall frames and glazing continued this period;
- Installation of waterproofing at the exterior of stairs “A” and “B” underway this period with interior drywall being applied at stair “A”;
- Piping to new boilers, hot water tank and chillers continues this period;
- MEPS inspection and sign-off by the DPW’s Building Official of classrooms on the first floor east side achieved this period.
- Lite gage framing and drywall substantially completed this period on the east side of the first floor;
- Installation of branch feeder wiring continues this period;
- Continued installation of the Exterior Metal Panel System;
- Interior painting on the third floor substantially completed this period;
- Installation of acoustical ceiling grid systems begun on the third floor;
- Cabling for the Data and Telephone systems continues on the third floor;
- Continued installation of revised storm and sewer structures as mandated by the Bridgeport WPCA;
- Installation of the ceramic tile in the toilet rooms on the third floor;
During the month of May the following significant construction activities will commence or continue:
- Commencement of the activation of the mechanical and electrical systems;
- Commencement of interior painting on the first floor;
- Commencement of the installation of acoustical ceiling grid systems on the first floor;
- Completion of the installation of revised storm and sewer structures as mandated by the Bridgeport WPCA;
- Installation of the ceramic tile in the toilet rooms on the first floor;
- Continued installation of the cabling for the Data and Telephone systems.
- Continued installation of the cabling for the AV Systems.
During this reporting period the General Contractor updated the Construction Schedule for Beacon Hall with a Data Date of March 31, 2008. This schedule indicates that the “Substantial Completion” will be achieved during the week of August 11. This is slip of about five weeks from the original date of July 5th. However, there is no further slippage of the forecasted completion date from our last report.
The General Contractor, Construction Administrator, and DPW continue to evaluate the construction schedule and associated activities to be sure that every avenue is being taken advantage of to be sure that the opening of Beacon Hall is on target and similarly that no issue is allowed to impact this goal.
In order to facilitate that goal the AV Trade Contractor mobilized and started their work during the week of April 7. In addition, it is anticipated that the Telephone/Communications Trade Contractor will mobilize on site on or about the week of June 2.
The Construction Administrator continues to meet throughout the month with the Project Team chairing the Owner’s Meetings and participating in the General Contractor’s Subcontractor Coordination Meetings.